Concrete is mixed in a lorry and poured on site. A cube test catches a bad batch.
Concrete is ordered by strength class, e.g. C30/37: 30 MPa on cylinders, 37 MPa on 150 mm cubes, as a 5% characteristic value. Every batch is checked by crushing cubes at 28 days.
EN 206 (first results, groups of 3): the mean must be at least $f_{ck} + 4$ MPa and every single result at least $f_{ck} - 4$ MPa.
Crush the three cubes (โถ). The machine reports the failure load F; strength is $f = F / A$ with $A = 150 \times 150$ mmยฒ.