Is it worth drilling?

Lesson Beginner

Join free to take this lesson

Anyone can look around, but taking a lesson needs a free account. With one, your answers are checked step by step and your progress is saved, so you can stop and pick up where you left off on any device.

3 steps · about 20 min · runs in the Testing lab

The ground is the one material you can't order. You have to go and find out.

The idea

Under every building is ground nobody has seen. A site investigation buys knowledge: a borehole (€2,000) shows the layers; a cone test (CPT, €700) is cheaper and continuous, but you have to interpret it: soft clay has a low cone resistance $q_c$ and a high friction ratio $R_f$.

Four columns of 900 + 450 kN go on this plot. If the ground surprises you after construction, repairs cost €250,000.

By the end you can

  • A site investigation buys knowledge: boreholes and cone tests.
  • Soft clay: low cone resistance, high friction ratio.
  • Probe before designing; use piles only where the ground needs them.