The critical path

Lesson Beginner

Join free to take this lesson

Anyone can look around, but taking a lesson needs a free account. With one, your answers are checked step by step and your progress is saved, so you can stop and pick up where you left off on any device.

5 steps ยท about 15 min ยท runs in the Construction lab

A building's finish date hides in one chain of activities. Find it and you control the project.

The idea

A construction programme is a network: foundations before the frame, the frame before the cladding. The critical path is the longest chain through it; it sets the finish date.

Every other activity has float: weeks it can slip without delaying the end. Forward pass: earliest starts; backward pass: latest finishes; float = latest start โˆ’ earliest start.

Crashing shortens an activity with overtime or extra crews, at a cost per week saved. It only helps on the critical path.

By the end you can

  • The critical path is the longest chain; it sets the finish date.
  • Other activities have float and can slip without delaying the end.
  • Crashing only helps on the critical path; float smooths the crews.