Building a road is mostly moving soil. The art is to move as little as possible.
A road over hilly ground is cut through the high ground and built up on embankments over the low ground. Digging, hauling and compacting soil is often the biggest cost of a new road.
Each cross-section's area comes from the depth d: a 12 m road with fill slopes of 1:2 has $A = 12 d + 2 d^2$. Volumes between sections 20 m apart: $V = \frac{A_1 + A_2}{2} \times 20$ (average end areas).
The mass-haul diagram adds up 0.9 ร cut โ fill along the road (cut soil compacts by 10%). Where it ends shows the surplus or shortfall; the area under it is how far the soil travels.